Bund Lining Works
Remediation of chemical storage bunds at a bulk liquid storage terminal.

Tank lining bund works for a major bulk storage provider. Works included sub-floor preparation and excavation, installation of coated GCL with a polyurea coating for chemical protection, protection geotextile, concrete canvas, 800 m of mechanical fixing, a 200 mm crusher layer, dust coverage and electrical leak detection testing.
What was involved
- Sub-floor preparation & excavation
- Coated GCL
- Polyurea coating
- Protection geotextile
- Concrete canvas
- 800 m mechanical fixing
- 200 mm crusher layer
- Dust coverage
- Electrical leak detection testing